Probabilistic yield expresses a solar system's expected annual output as exceedance values. P50 is the yield the system is expected to exceed in half of all years, P90 in nine years out of ten and P99 in ninety-nine out of a hundred, so a lender or buyer can see the downside, not just the average.
A single yield figure hides the fact that solar output varies from year to year. Probabilistic yield describes that variation with exceedance values. The P50 is the median: the annual yield the system is expected to exceed in half of all years. P90 is the yield it should exceed in nine years out of ten, and P99 in ninety-nine years out of a hundred.
Two kinds of uncertainty go into it. The first is the weather: some years are sunnier than others. The second is the estimate itself: the irradiance data, the simulation model, soiling, degradation assumptions and system losses each carry an uncertainty. Combined, typically as the root sum of squares, they give the standard deviation around the P50.
The lower values are what lenders use. Debt for solar projects is commonly sized on P90 or P99, because the loan must be repaid in a poor year too. Equity investors look at P50. A wide gap between P50 and P90 signals an uncertain estimate.
They need a good starting point. The P50 is only as good as the simulation behind it, and the weather variability needs a long series of measured or modelled years, which is why probabilistic figures are usually built on typical meteorological year data.
Why it matters for solar installers
Commercial buyers and financiers increasingly ask for more than one yield number. SolarVis computes P50, P90 and P99 by combining the interannual variability of PVGIS weather data with the modelling uncertainty you set. The analysis runs when the design uses the PVGIS typical meteorological year as its data source. See 3D design and simulation.
Sık sorulan sorular
- What does P90 mean for a solar project?
- P90 is the annual energy yield the system is expected to exceed in 90 percent of years. It is lower than the P50 median and is commonly used by lenders and investors to size debt, because it reflects a bad year rather than an average one.
- How are P50 and P90 calculated?
- The P50 comes from the yield simulation. The spread around it combines the year-to-year variability of the weather with the uncertainties of the model, the irradiance data and the system losses. Assuming a normal distribution, P90 lies about 1.28 standard deviations below the P50 and P99 about 2.33.
- Should a residential proposal show P90?
- It helps with cautious buyers and with financed projects. Showing the median alongside a conservative case sets honest expectations, and a customer who has seen the P90 figure is less likely to complain after a cloudy year.