G99 (Engineering Recommendation G99)

G99 is the Energy Networks Association's Engineering Recommendation for connecting generation, including solar and batteries, to the distribution network in Great Britain. A system whose total generation exceeds 16 A per phase needs a G99 application and the network operator's approval before it is installed.

Also known asG99EREC G99G99 applicationG98DNO application

G99 is Engineering Recommendation G99, published by the Energy Networks Association (ENA). It sets the technical requirements for connecting generating equipment, solar PV and battery storage included, in parallel with a distribution network in Great Britain, and the process for getting that connection approved by the distribution network operator (DNO).

The threshold is 16 A per phase. Small systems up to 16 A per phase, roughly 3.68 kW on a single-phase supply, with type-tested equipment fall under the simpler G98: the installer connects them and notifies the DNO within 28 days. Above that, the project is a G99 connection and the DNO has to accept the application before the system is installed.

The limit counts everything on site. Solar inverters and battery inverters are added together. A modest solar system that was a G98 job becomes a G99 job once a battery is added, which affects both timing and design.

The DNO studies the network. For a G99 application the operator checks whether the local network can take the extra generation. It may approve the connection, approve it with an export limit, or require reinforcement. An export limitation scheme is often how a larger system gets approved without network upgrades.

Paperwork decides the timeline. Incomplete applications are returned, and a missing or inconsistent single line diagram is one of the usual reasons.

Why it matters for solar installers

G99 timelines can hold up an otherwise ready project for weeks, so the application has to be right the first time. SolarVis generates the single line diagram from the stringing design, with the inverters, battery, protection and grid connection on your own title block, and keeps it in step with the design as it changes. See single line diagram.

Common questions

What is the difference between G98 and G99?
G98 covers small systems up to 16 A per phase, about 3.68 kW on a single-phase supply, with fully type-tested equipment. They are connected first and notified to the network operator within 28 days. Anything larger falls under G99, which requires an application and the operator's acceptance before installation.
Does a battery count toward the G99 threshold?
Yes. The 16 A per phase limit applies to all generation at the premises together, and a battery inverter that can export counts as generation. Adding a battery to a solar system is a common reason a project moves from G98 to G99.
What does a G99 application include?
The network operator's application form, details of the generating and storage equipment with their type-test information, the site's connection details and a single line diagram showing how the system connects and is protected. Where export is to be limited, the export limitation scheme is described as well.

Put this to work in solarVis

Last updated November 10, 2026
Get started

See solarVis in action

We use cookies to improve solarVis

Necessary cookies keep the site running. Analytics and marketing cookies show us which pages actually help installers and let us measure our ads. We enable analytics and marketing cookies by default to improve this site and measure our ads. You can opt out anytime. Read our Cookie Policy